Quality control procedures are fully documented and available for client inspection. Also available is certification of construction methods in accordance with the American Society of Mechanical Engineers (ASME) code: pressure vessels, and for activities in compliance with the Alberta Safety Codes Act and the following referenced standards:
It has been a long-standing principle at BWS FABRICATION INC. that deficiencies observed in third party supplied work or materials will be flagged and rectified - subject to the appropriate client authorization and whether or not they are necessarily within the bounds of the contract.
Quality Assurance / Quality Control Manual |
Yes |
| Title: |
|
|
|
- Quality Control Manual for construction activities in accordance with the American Society of Mechanical Engineers (ASME) code: Section Vlll, Div 1; Pressure Vessels 2007
|
|
| Organization: |
|
|
- Is the Inspector/QA Group independent of the organization that is responsible for performing the activity?
|
Yes |
| Design Control: |
|
|
- Is the adequacy of the design checked?
|
Yes |
|
- Are design requirements correctly translated into specifications, drawings, procedures and instructions?
|
Yes |
| Procurement Document Control: |
|
|
- Is the adequacy of the design checked?
|
Yes |
|
- Are the applicable requirements and design bases included in the procurement drawings?
|
Yes |
| Instruction, Procedure and Drawings: |
|
|
- Do procedures and instructions include acceptance criteria?
|
Yes |
| Document Control: |
|
|
- Are obsolete documents controlled?
|
Yes |
| Control of Purchased Material, Equipment and Services: |
|
|
- Is purchased material checked for conformance to procurement documents?
|
Yes |
| Identification and Control of Material, Part and Services: |
|
|
- Is identification controlled throughout fabrication?
|
Yes |
| Control of Special Processes: |
|
|
- Are qualified procedures available for special processes?
|
Yes |
Inspection: |
|
|
ls inspection performed by individuals other than the ones doing the actual work? |
Yes |
ABSA & Third Party Test Control: |
|
|
- Do test procedures define and establish the acceptance criteria?
|
Yes |
| Quality Assurance Program: |
|
|
- Is there control over activities affecting quality?
|
Yes |
| Control of measuring equipment: |
|
|
- Is calibration performed to written procedure?
|
Yes |
|
- Are specified periods of calibration documented?
|
Yes |
| Handling Storage and Shipping: |
|
|
- Are procedures available for handling, storage & shipping?
|
Yes |
| Inspection, Test and Operating Status: |
|
|
- Are inspection and test results monitored as fabrication is being performed?
|
Yes |
Non-conforming Materials, Parts or Components: |
|
|
- ls re-inspection performed on repaired or reworked items?
|
Yes |
| Corrective Action: |
|
|
- Are causes of significant conditions identified and, are actions to preclude repetition promptly implemented, documented and reported to management?
|
Yes |
Quality Assurance Records: |
|
|
- Is there a procedure that identifies what records are to be maintained?
|
Yes |
| Audits: |
|
|
- Are periodic audits required to verify compliance of the QA Program?
|
Yes |
|
- Are results reviewed by the management?
|
Yes |
|
- Are re-audits performed to ensure corrective action?
|
Yes |
|
|
|
|
|
|